Elementary School Modernization Project, Group 1, Phase 2 (2024)


Overview: The modernization project seeks to upgrade our outdated campuses (some originally built in 1950’s). Through this project we are modernizing the existing classrooms and buildings with new LVT flooring (no more waxing!), replacement in kind of HVAC units, new FRP doors and new tackboards, white boards casework and furniture for each room and office. Libraries, classrooms, and offices are getting reconfigured and provided new furniture to allow the old existing rooms, to work as new functional workspaces. New Emergency communication systems and upgraded electrical and data infrastructure allow the campuses to function on a more immediate basis. Combined with all the work on the interior, each campus will receive a full exterior painting of the campus.
Scope: The scope includes 3 elementary schools across the district, tackling the entire site including classrooms, libraries, and staff areas. This is the first phase of the group.
Meadow Homes: This project consists of reconfiguration of the library and admins spaces in building B1 as well as Accessibility upgrades at two restrooms in building E. Flooring in kind replacement will take places as well as HVAC unit upgrades (in kind). New interior lighting throughout the campus will be installed. Interior and exterior painting will be completed throughout the buildings. The existing tackboards and marker boards will be replaced with new. Additional scope includes new outdoor drinking fountains and bottle fillers along with accessibility upgrades at the staff parking lot.
Mt. Diablo: The campus will receive new flooring in kind replacement with new material, new casework with accessible sinks. New interior lighting throughout the campus will be installed. The IT infrastructure will continue to be upgraded in this Increment as well as door replacement to the new FRP door standard. Interior and exterior painting will be completed throughout the buildings. The existing tackboards and marker boards will be replaced with new.
Rio Vista: The campus will receive new flooring in kind replacement with new material, new casework with accessible sinks. New interior lighting throughout the campus will be installed. The IT infrastructure will continue to be upgraded in this Increment as well as door replacement to the new FRP door standard. Interior and exterior painting will be completed throughout the buildings. The existing tackboards and marker boards will be replaced with new. A new playground will be installed along with new striping and blacktop resurfacing in the back of campus.
| Location: |
Meadow Homes Elementary School Mt. Diablo Elementary School Rio Vista Elementary School |
|---|---|
| Estimated Cost: | $17,761,187 |
| Contractor: | Arntz Builders, Inc. |
| Funding Source: | Measure J, School Safety and Classroom Improvement Measure |
| Bid Number: | #1945 |
| Construction Manager: | Sixth Dimension PMCM, Inc. |
Project Progression Photos